1-24
COMMISSIONING
1. CHECKLIST BEFORE COMMISSIONING
Do NOT operate the system before the following checks are OK:
The indoor unit is properly mounted.
The outdoor unit is properly mounted.
The system is properly earthed and the earth terminals are tightened.
The fuses or locally installed protection devices are installed according to this document, and have NOT been
bypassed.
The power supply voltage matches the voltage on the identication label of the unit.
There are NO loose connections or damaged electrical components in the switch box.
There are NO damaged components or squeezed pipes on the inside of the indoor and outdoor units.
There are NO refrigerant leaks.
The refrigerant pipes (gas and liquid) are thermally insulated.
The correct pipe size is installed and the pipes are properly insulated.
The stop valves (gas and liquid) on the outdoor unit are fully open.
The following eld wiring has been carried out according to this document and the applicable legislation between the
outdoor unit and the indoor unit.
Drainage
Make sure drainage ows smoothly.
Possible consequence: Condensate water might drip.
The indoor unit receives the signals of the user interface.
The specied wires are used for the interconnection cable.
2. CHECKLIST DURING COMMISSIONING
To perform an air purge.
To perform a test run.

Table of Contents

Other manuals for Daikin FTXC71BV1B

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Daikin FTXC71BV1B and is the answer not in the manual?

Daikin FTXC71BV1B Specifications

General IconGeneral
BrandDaikin
ModelFTXC71BV1B
CategoryAir Conditioner
LanguageEnglish

Related product manuals