Eaton® 9390 (100–160 kVA) UPS Installation and Operation Manual 164201604—Rev F 24
4. Reinstall the conduit landing plate and install the conduit.
5. Route and install the LAN, telephone, and other cables to the appropriate X-Slot cards.
6. When all wiring is complete, reinstall the safety shield panels removed in previous steps. Secure with the
retained hardware.
7. Close the control panel door and secure with the retained hardware.
8. Reinstall the doors removed previously and secure with the retained hardware.
9. Close the doors and secure the latch.
10. Refer to the manual supplied with the X-Slot card for operator instructions.
44..88..44 IInnssttaalllliinngg AAcccceessssoorriieess aanndd PPaarraalllleell SSyysstteemm CCoonnttrrooll WWiirriinngg
To install an optional Remote Emergency Power-off (REPO) Control, see
Chapter 5 Installing a Remote Emergency Power-off Control. To install optional accessories and to install
parallel system control wiring, see Chapter 6 Installing Optional Accessories.
44..99 IInniittiiaall SSttaarrttuupp
Startup and operational checks must be performed by an authorized Eaton Customer Service Engineer, or the
warranty terms become void. This service is offered as part of the sales contract for the UPS. Contact service
in advance (usually a two-week notice is required) to reserve a preferred startup date.
44..1100 CCoommpplleettiinngg tthhee IInnssttaallllaattiioonn CChheecckklliisstt
The final step in installing the UPS system is completing the following installation checklist. This checklist
ensures that you have completely installed all hardware, cables, and other equipment. Completing all items
listed on the checklist will ensure a smooth installation. You should make a copy of the installation checklist
before filling it out, and retain the original.
After the installation is complete, a service representative will be able to verify the UPS system operation and
commission it to support the critical load. The service representative cannot perform any installation tasks other
than verifying software and operating setup parameters. Service personnel may request a copy of the
completed installation checklist to be sure you have completed all applicable equipment installation.
NNOOTTEE The Installation checklist MUST be completed prior to starting the UPS system for the
first time.
Installing the UPS System