Eaton® 9390 (100–160 kVA) UPS Installation and Operation Manual 164201604—Rev F 28
CChhaapptteerr 55 IInnssttaalllliinngg aa RReemmoottee EEmmeerrggeennccyy PPoowweerr--ooffff CCoonnttrrooll
A latching-type Remote Emergency Power-off (REPO) switch can be used in an emergency to shut down the
UPS and remove power to the critical load from a location away from where the UPS is installed. Figure 5
shows an Eaton REPO switch.
FFiigguurree 55.. EEaattoonn RREEPPOO SSwwiittcchh
55..11 RREEPPOO IInnssttaallllaattiioonn
NNOOTTEE Before installing a REPO switch, verify that the UPS was installed according to the
instructions in Chapter 4 Installing the UPS System.
To install a REPO station:
1. Verify that the UPS system is turned off and all power sources are removed. See
Chapter 9 UPS Operating Instructions for shutdown instructions.
2. Securely mount the REPO station. Recommended locations include operator's consoles or near exit doors.
See Figure 88 for enclosure dimensions and wiring knockouts.
3. Install wiring from the REPO station using 1/2-inch conduit through the cable entry knockout in the top of
the UPS cabinet. See Chapter 15 Installation Information for conduit landing area, terminal board location,
and terminal wiring assignments.
4. Connect the REPO wiring as shown in Table 1 and Figure 6.
For Internal Use Only