P-164000477 9395P750 kVA / 900 kVA and 1000 kVA / 1100 kVA 50
Revision 002 User’s and Installation Guide
Figure 4-14. Conduit and wire entry locations
ATOP VIEW 3 x UPM Section
BTOP VIEW ISBM
CBOTTOM VIEW ISBM
1 Ventilation Grill Debris Shields
2 Top entry conduit landing for AC anput and output, and DC input (Remove panel
to drill or punch cable entry holes.)
3 Interface entry conduit landings for TB1 through TB3 wiring and X-Slot connec-
tions (Remove panels to drill or punch cabel entry holes.)
4 Bottom entry conduit landing for AC input and output, and DC input (Remove
panel to drill or punch cable entry holes.)
A
1