48 Eaton Power Xpert 9395 UPS Installation and Operation Manual 164201764—Rev 14
1. If not already accomplished, use a forklift or pallet jack to move the ISBM and UPM sections to the
installation area, or as close as possible, before unloading from the pallets. If possible, move each section
using the pallet. Insert the forklift or pallet jack forks from the right side of the pallet (facing the cabinet),
between the supports on the bottom of the pallet (see Figure 11, for the ISBM and UPM section center of
gravity measurements). If the sections must be moved using the cabinet front or rear fork lift slots, see the
caution statements at the beginning of this procedure.
2. Remove the three bolts securing the left side shipping bracket to the cabinet and three bolts securing the
bracket to the pallet (see Figure 16, or Figure 18). Remove the left side shipping bracket. If installing the
cabinet permanently, retain the shipping bracket and securing hardware for later use.
3. Remove the three bolts securing the right side shipping bracket to the cabinet and three bolts securing the
bracket to the pallet (see Figure 17, or Figure 19). Remove the right side shipping bracket.
Figure 16. Removing the ISBM Section Left Side Shipping Bracket
Shipping Bracket
Bolts
Shipping Bracket
Bolts
Pallet
Left Side Shipping
Bracket
Front Door
UPS System Installation