SECTION 3 PCM-875A Mechanized Plasma Cutting System Installation
3-1
3.1 General
Proper installation is important for satisfactory and
trouble free operation. Follow these instructions
carefully.
WARNING
!
Failure to follow these directions
carefully may lead to injury or death.
Read this entire manual before
proceeding.
Damage to property or equipment may occur.
3.2 Installation of the PCM-875A Power Console
3.2.1 Equipment Required
A source of clean dry air at 153,4 liters/minute at
5,2 to 5,9 bar. The maximum inlet pressure of the
air filter-regulator is 10,4 bar and should not be
exceeded.