2. Commissioning
2-40
Festo P.BE-CPX-FB32-EN en 1111a
2.5 C heck list for commissioning the CPX terminal with FB32
• Please observe the general commissioni ng instructions in
the CPX system description.
• Ch eck the DIL switch settings and the network
configuration before using and replacing CPX terminals.
• Che ck the configured address range. If necessary,
test the I/Os.
• Check the address assignment of the I/Os on the CPX
terminal. For this purpose you can, if necessary,
force the I/Os (see CPX system description).
• Make sure that the desired parameterisation of the CPX
terminal in the start-up phase or after fieldbus
interruptions is restored by the plug-in module.
This is to ensure that if the CPX terminal is replaced, the
new terminal will also be operated wi th the desired
parameter setti ngs.
• Use spot checks if necessary to check the
parameterisation, e.g. with the configuration program or
with the Handheld.