2. Commissioning
2-40
Festo P.BE-CPX-FB32-EN en 1111a
2.5 C heck list for commissioning the CPX terminal with FB32
Please observe the general commissioni ng instructions in
the CPX system description.
Ch eck the DIL switch settings and the network
configuration before using and replacing CPX terminals.
Che ck the configured address range. If necessary,
test the I/Os.
Check the address assignment of the I/Os on the CPX
terminal. For this purpose you can, if necessary,
force the I/Os (see CPX system description).
Make sure that the desired parameterisation of the CPX
terminal in the start-up phase or after fieldbus
interruptions is restored by the plug-in module.
This is to ensure that if the CPX terminal is replaced, the
new terminal will also be operated wi th the desired
parameter setti ngs.
Use spot checks if necessary to check the
parameterisation, e.g. with the configuration program or
with the Handheld.