EasyManua.ls Logo

GE 750 - Measurement of Current Demand

GE 750
504 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
GE Power Management 750/760 Feeder Management Relay 17-
17
17 COMMISSIONING 17.6 METERING
17
17.6.7 MEASUREMENT OF CURRENT DEMAND
Test Connections per Figure 17–1: RELAY TEST WIRING – WYE CONNECTION or Figure 17–2: RELAY
TEST WIRING – DELTA CONNECTION on page 17–4.
Expected Accuracy:
± 2.0% of full scale
To reset the "Last Demand" reading to 0 between tests, cycle the relay power source off/on.
Block Interval and Rolling demand measurement types must be tested in synchronization with the internal
clock. Both of these measurements start with the first interval of the day at 12:00:00.000 midnight. To synchro-
nize, preset the injection levels, then turn the current off. Select the relay display (not the 750/760PC program)
to
A1 STATUS \ CLOCK \ CURRENT TIME
. Apply the test current when the clock is at the beginning of an interval
measurement period, as determined by the
TIME INTERVAL
setpoint for the element.
Actual Values Displays:
Under subheading
A2 METERING \ DEMAND \ PHASE A CURRENT \
LAST PHASE A CURRENT DEMAND
MAX PHASE A CURRENT DEMAND
(DATE, TIME)
Under subheading
A2 METERING \ DEMAND \ PHASE B CURRENT \
LAST PHASE B CURRENT DEMAND
MAX PHASE B CURRENT DEMAND (DATE, TIME)
Under subheading
A2 METERING \ DEMAND \ PHASE C CURRENT \
LAST PHASE C CURRENT DEMAND
MAX PHASE C CURRENT DEMAND (DATE, TIME)
Procedure:
Thermal Exponential Demand: (Example for a response time setting of 5 minutes.)
1. Clear demand data registers by entering
Yes
at
S1 RELAY SETUP \ CLEAR DATA \ CLEAR MAX DEMAND DATA?
2. Inject a fixed value of current into phase A. Record the measured current demand at 1, 2, 3, 4, 5 and 10
min. after the application of current. The demand, in percent of injected current, should be as follows:
3. For other response time settings, multiply the row 1 times above by [selected response time
÷
5].
4. Check that the maximum current demand, including date & time of occurrence, is recorded and displayed.
5. Repeat steps 2 to 4 for phases B and C.
Block Interval Demand: (Example for a time interval setting of 5 minutes.)
Repeat steps 2 to 5 from Thermal Exponential Demand. Record the measured current demand at 1, 2, 3, 4, 5
and 6 min. after the application of current. The demand, in percent of injected current, should be as follows:
Time (min.) 1 2 3 4 6 10
Demand (% of Input) 36.9 60.1 74.8 84.1 90.0 99.0
Time (min.) 1 2 3 4 5 6
Demand (% of Input) 0.0 0.0 0.0 0.0 100.0 100.0

Table of Contents

Other manuals for GE 750

Related product manuals