5.2 Install disposable flow kits
I
ntroduction
This section describes how to install the flow kit and the gradient section.
The installation is divided into several procedures that are recommended to be per-
formed in the following sequence:
1. Prepare the system for flow kit installation.
2. Install the pump chamber - pull out the pump wagon and install one pump
chamber for an isocratic setup and two pump chambers for a gradient setup.
3. Position the inlet manifold - position the A inlet manifold for an isocratic setup
and both the A and B inlet manifold for a gradient setup.
4. Install the jumper tubing - install the jumper tubing for the gradient setup only.
5. Position the air trap tubing.
6. Install the inlet manifolds and air trap tubing - install the A inlet manifold for an
isocratic setup and both the A and B inlet manifold for a gradient setup.
7. Position and install the column tubing.
8. Position and install the outlet manifold.
9. Install system components to the flow kit.
10. Connect the sensors.
Prerequisites
It is recommended that two people work together to perform the installation.
The tool kit provided with the delivery is required in the installation procedure.
Prepare the flow kit for
installation
NOTICE
O
pen the plastic bags carefully so that you do not damage the
flow kit components.
Always open the plastic bags in a clean environment.
Note: Make a note of each flow kit serial number. Each serial number needs to be
e
ntered as part of the installation test later.
5 Preparation
5
.2 Install disposable flow kits
ÄKTA ready XL Operating Instructions 29281616 AE 97
*** TeDIS Valid on Date Printed Printed on: 15-09-2023 11:27:35 ***

Table of Contents

Related product manuals