CHAPTER 5: SETTINGS CONTROL ELEMENTS
F35 MULTIPLE FEEDER PROTECTION SYSTEM – INSTRUCTION MANUAL 5-291
5
BRK 1 FLSHOVR SPV A to BRK 1 FLSHOVR SPV C — These settings specify FlexLogic operands (per breaker pole) that supervise
the operation of the element per phase. Supervision can be provided by operation of other protection elements, breaker
failure, and close and trip commands. A six-cycle time delay applies after the selected FlexLogic operand resets.
BRK FLSHOVR PKP DELAY — This setting specifies the time delay to operate after a pickup condition is detected.