GE HEALTHCARE OPTIMA XR200AMX/XR220AMX
D
IRECTION 5336113-1EN, REVISION 10 INSTALLATION MANUAL
Page 34 Section 3.2 Unpacking the system
Figure 3-1 Optima XR200amx/Optima XR220amx installation workflow
Section 3.2 Unpacking the system
Within the United States, the Optima XR200amx/Optima XR220amx is shipped on its own wheels,
with minimal packaging. External to the United States, the Optima XR200amx/Optima XR220amx
is shipped in a packing crate.
To prepare the unit for installation, follow these steps:
SYSTEM INSTALLATION WORKFLOW
Upack
the system
Does the
power plug meet
requirements?
No
Yes
Ready for
configuration
and
calibration
Replace the
power plug
Plug in and
turn on
system power
Install
optional
hardware
Is the
system an
Optima
XR220amx?
No
Install the
detector
Yes
Perform
ground and
leakage
testing