NOTE: The PDB shall include the switch allowing the commutation of generator supply to the
UPS. Neutral shall be fed by the hospital. The customer provides the cables A, B and
C.
NOTE: Refer to the UPS vendor Service manual Installation Guide SG Serie 10, 20, 30 & 40
kVA for more details
Innova 2100-IQ, 3100/3100-IQ, 4100/4100-IQ Cardiovascular Imaging System Pre-Installation Manual
GE Healthcare Direction 5160944-13-1EN, Revision 2
Chapter 6 Electrical Connections 167