Locate the position of the IVUS components in the Control Room, according to the workflow
requirement of the operators.
Establish a 76 mm (3”) conduit below floor from the IVUS CPU location in the Control Room,
to the foot end area of the Patient Table in the Procedures Room:
Locate the Procedures Room exit of the conduit close to the centerline of the Patient Table
Locate it as close to the Patient Table base as possible, considering :
Room for access to the table for service purposes
Limitation from other cables connected to the table
Location of the table plate
Location of Mac-Lab conduit
Location of Physio or Med Gases connections
The IVUS cables are moving cables, they have to allow the Patient Table motions
(Panning, Lifting and Rotating)
Use similar solutions (i.e. protection against cleaning fluids, etc. ) as it is used for the Mac-Lab
conduit
See also guidance on Typical Layout drawing 4-58f sheets E1 and S2, showing Mac-Lab and
P/M Gas location recommendations.
6.3 Run Interconnection cables through the Conduit
Use the IVUS Rev 2 PIM (#806365002) as reference to the procedures below.
Unpack , and check the completeness of the Preinstallation kit :
1 pcs - Custom PIM cable 30 m (98 ft, 5 in) - Volcano ID :806452001
1 pcs - CAT5 cable 30 m (98 ft, 5 in) - Volcano ID :807055001
1 pcs - Custom Twin axial cable - Volcano ID :806380001
1 pcs - Ground Cable, 30 m (98 ft, 5 in) s5i – Volcano ID :806889001
1 pcs - IVUS Rev 2 Preinstallation Manual - Volcano ID :806365002
Install 806889001 Ground Cable through the Control Booth conduit (see note)
Install the cables through the IVUS conduit from the Control Room end :
806452001 PIM cable, round shaped connector end to the Procedures Room
807055001 - Ethernet cable (1 pcs)
Install the optional cables through the IVUS conduit from the Control Room end :
806380001 - ECG cable in case, if NON Mac-Lab ECG will be installed
808631002 – FFR cable option - 15m
808632002 – FFR cable option - 27m
NOTE: For the ground cable, see the IVUS Rev 2 service manual for special
instructions concerning cable running and cutting .
NOTE: If the installation has the MaC-Lab ECG in the configuration, the ECG cable
shall not be run through the conduit, it will be used in the Control Room to
connect Mac-Lab and IVUS PCs.
Innova 2100-IQ, 3100/3100-IQ, 4100/4100-IQ Cardiovascular Imaging System Pre-Installation Manual