6 IVUS Rev 2 Option
6.1 Wiring Diagram
The connection cables between the IVUS Control Room and Procedures Room components run
in a dedicated under floor conduit (see Section 6.2).
A GND wire between the C1 cabinet and the IVUS Rev 2 CPU runs in the underfloor conduit
prepared for the Control Booth cables between Equipment Room and Control Room.
Illustration 6-14:
6.2 IVUS Floor Conduits
A 3 inches and max. 25 m long conduit between Control and Patient Rooms shall be prepared
below the floor for the IVUS Innova interconnection cables.