CF-9 User's Guide
09/30/92 GPD Global 19
Process Components
1. Position component reel or ammo pack of taped components in reel holder.
2. Load components. Refer to Load Components on page 18.
3. Close safety shield and press reset button.
4. Run machine very slowly to verify proper adjustment. Make further adjustments if
necessary to achieve desired results.
C A U T I O N
Testing component position relative to dies MUST be done prior to automatic
machine operations.
5. Increase machine speed rate to desired setting and process components.
6. To process a different component form or type, repeat Setup procedure on page 13.
Power Off
1. Set speed control to zero (0).
2. Turn power switch to OFF.
3. Remove all dies and clean with a rust inhibitor and lubricate mechanical moving
parts per Preventive Maintenance.