18
COMMISSIONING POWERED OPERATION
1. Preliminary Checks
Before electrical wiring, complete following checks:
Clear swarf and all other residual debris
Verify security of all fixings
Control Board Layout
Fig.19 Control board layout
A. Display Orientation
B. Display and push buttons
C. Primary Function Dip switches
D. PC connector
E. Transformer plug connector
F. Battery connector
G. ON-OFF Switch connector
H. Integral Mode switch plug
I. Auxiliary Outputs
J. Input connections
K. Auxiliary power output
L. Pair & adv. mode selector link
M. Lock power output
N. Encoder
O. Motor
P. Brake Level
Q. Arm Type selector