Loading...
9. Install the M.2 SSD enablement board.
10. Install the riser cage.
11.
Connect the SATA cables.
12.
Install the access panel.
13.
Install the server into the rack.
14.
Connect all peripheral cables to the server.
15.
Connect each power cord to the server.
16.
Connect each power cord to the power source.
17.
Power up the server.
The installation is complete.
ODD options
Installing the ODD in LFF
Procedure
1. If installed, remove the bezel.
2. Power down the server.
3. Remove all power:
a. Disconnect each power cord from the power source.
b. Disconnect each power cord from the server.
4. Disconnect all peripheral cables from the server.
5. Do one of the following:
Hardware options installation 75