6.2.1.1.2 Installing DC Power Cables
Precautions
● It is recommended that switches be installed for battery cables. Customers
need to purchase switches by themselves. For details about the battery circuit
breaker specications, see 4.1.3 Power Cables.
● Install battery cables in the following sequence: 1. Install cables at the battery
terminals on the UPS side. 2. Install cables at the battery terminals on the
battery side.
Procedure
1. Install battery cables.
– External battery strings
UPS2000-G-(6 kVA–20 kVA)
User Manual (Lead-Acid Battery) 6 Operations
Issue 23 (2024-03-15) Copyright © Huawei Digital Power Technologies Co., Ltd. 120