b) In the navigation area, expand System Service Aids > Cable Plugging Validation. Then, click
Validate Cables. The system veriîš³es that the expected cables are present.
c) If your conîš³guration includes two or more nodes, expand System Service Aids > Cable Plugging
Validation. Then, click Verify Node Position. Otherwise, if your conîš³guration includes only one
node, continue to the next step.
If the system is cabled correctly, the blue identify LED on each system node will light up, in
sequence, from the top node to the bottom node. If the LEDs do not light up in sequence, the FSP
cables need to be re-installed.
d) Expand System Service Aids > Cable Plugging Validation. Then, select All of the above in the
Display Cable Status section and click Continue. The system validates that the cables are installed
in the correct locations. Expand System Service Aids > Cable Plugging Validation to display a
table with the results. Ensure that the plugging status is OK for each cable in the displayed table. If
the status is OK, no further action is required. If the status is not OK, review the error logs, correct
the problems, and repeat steps b, c and d as needed until the status is OK for all cables.
e) Exit the ASMI.
NVMe backplane 397

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the IBM 9080-M9S and is the answer not in the manual?

IBM 9080-M9S Specifications

General IconGeneral
BrandIBM
Model9080-M9S
CategoryPower Supply
LanguageEnglish

Related product manuals