1.28 APPLIANCE STARTUP IGNITION
To commission the boiler (the operations listed below must only be performed by qualied personnel and in the presence of sta only):
1. check that the internal system is properly sealed according to the specications set forth by regulations in force;
2. Ensure that the type of gas used corresponds to the boiler settings (the type of gas appears on the display on rst connection to the
power supply, or by checking the relative parameter “G”);
3. check that there is no air in the gas pipe;
4. Check connection to a 230V~50Hz power mains, correct L-N polarity and the earthing connection;
5. check that the intake/exhaust terminals are not obstructed and that they are installed properly;
6. Check that the drain trap is full and that it prevents any passage of ue gas into the room;
7. check that there are no external factors that may cause the formation of fuel pockets;
8. Perform the ue test and, if needed, set the correct value of the parameter “F0”:
9. Activate the quick Calibration function:
10. Switch the appliance on and check correct ignition;
11. Check that the gas ow rate and the relative pressure values comply with those indicated in the booklet;
12. ensure that the safety device intervenes in the event of gas supply failure and check the relative intervention time;
13. Check the activation of the main switch located upstream of the appliance and in the appliance.
Even if just one single safety check provides a negative result, do not commission the system.