Exercise the meter for 10 to 15 minutes before proving the meter.
6. Close the nozzle.
7. Unclamp the meter by pressing the Chuck Valve button.
8. Exit Operate Valves and Observe Sensor Readings.
Setting Up the Measurement Systems Prover
1. Open the MMS prover application.
2. Select Meter Setup Menu.
11 December 2019 TDC-1782-005 44
Intelis Gas Meter Installation Guide 5 îProving