7.11 Preparing the mounting site
Before installing the unit, carry out the following:
1. Check that the foundation is level and has the necessary strength.
2. Check that all access roads are wide enough for the unit to pass, see the dimension
sketches.
3. Block the mounting site. The site must be blocked to prevent unauthorised personnel from
being injured or causing damage.
4. Clear the mounting site.
7.12 Space requirements
When installing the unit, make sure that the plant can be serviced without problems, i.e. always
make sure that there is enough space around the plant. See subsection 6.4 Planning the machine
room.
7.13 Lifting accessories and equipment
See chapter 14. Transport instructions.
7.14 Preparing lifts
See chapter 14. Transport instructions.
7.15 Lifting and loading instructions
See chapter 14. Transport instructions.
7.16 Unpacking and inspection
See chapter 14. Transport instructions.
7.17 Disposal of non-reusable materials
Materials from the unit packing which cannot be reused must be disposed of according to local
regulations.
7.18 Moving the equipment to the mounting site
After unloading and unpacking
See chapter 14. Transport instructions.