9. With two or more persons, take the bag
from the inside of the folds and mount
it above the basket, passing it “5 cm”
(2 in) towards the tunnel Fig. 34 (as a
way that the upper side ts above the
hanger and the lower side is supported
on the ground).
10. Raise up the basket “A” Fig. 35, to the
maximum height, (parallelogram in
contact with the tunnel).
11. Verify that the stretching reference is
located at the side of the machine (tun-
nel), if not rotate bag over the basket.
12. Control the lower part of the bag in
contact with the ground, it has to be
centeredwith the tunnel.
13. Raise the machine from the tractor re-
mote control to its maximum height.
14. Slide bag from the hanger towards the
tunnel and from the upper central part
to the sides. Do these until 50 % of the
folds width is mounted over the tunnel
Fig. 36.
Manipulate the bag with care so thet
the folds don´t get disarranged.
FIG.34
FIG.35
FIG.36