EasyManua.ls Logo

Manitowoc MAX-ER 16000 - Install Hanging Counterweight Assembly; Prepare Beam Assembly

Manitowoc MAX-ER 16000
186 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Reference Only
Manitowoc Published 04-17-17, Control # 067-11 4-47
16000 HANGING MAX-ER® OPERATOR MANUAL SET-UP AND INSTALLATION
4
Install Hanging Counterweight Assembly
Prepare Beam Assembly
See Figure 4-25 for the following procedure.
The beam assembly and inserts can be shipped in any of the
assembled configurations shown in Figure 4-25
.
Determine beam length based on your lifting requirements:
36.1 ft (11 m) Working Position (View A)
42.7 ft (13 m) Working Position (View B)
49.2 ft (15 m) Working Position (View C)
1. Lift beam assembly (1) off trailer and place it on blocking
in assembly area (View F).
Lift only as shown in Views A through D.
2. If necessary, attach required beam inserts (2) to beam
assembly (1) with pins (7, View E).
Make sure beam inserts (2) are positioned as shown in
View F.

Table of Contents

Related product manuals