SET-UP AND INSTALLATION 16000 HANGING MAX-ER® OPERATOR MANUAL
4-58
Published 04-17-17, Control # 067-11
Connect Beam to Counterweight — SEQUENCE 2
See Figure 4-30 for the following procedure.
1. Remove ladder (2, View C) from beam assembly (1):
a. Remove snap pins (3) from storage holes.
b. Slide ladder out of hooks (4) and remove ladder.
c. Reinstall snap pins in storage holes.
2. Connect lifting slings from assist crane to proper lifting
lugs on beam assembly (see Figure 4-25
).
3. Lift beam assembly high enough to allow installation of
ladder (2).
4. Install ladder (2) in slots (5, View F) on right side of beam
assembly.
5. Lift beam assembly into position over counterweight tray
(6).
6. Align connecting holes in beam assembly (1, View D)
with connecting holes in counterweight tray (6).
7. Install pins (7, View A).
8. Lower beam support (8, View D) to assembly position:
a. Using hand winch (9, View B), rotate handle until
lifting cable (10) is taut and pins (11, View E) are
loose.
NOTE The hand winch has an automatic brake which
applies to hold the beam support in position when
you stop turning the handle.
b. Remove pins (11, View E) from stored position.
c. Using hand winch, lower beam support to assembly
position and install pins (11, View G).
9. Lower beam assembly onto beam support.
10. Disconnect lifting slings and remove assist crane.