16000 HANGING MAX-ER® OPERATOR MANUAL SET-UP AND INSTALLATION
4
Remove Top from Shipping Position
See Figure 4-5 for the following procedure.
1. Check that retaining pins (1, View E) are installed in
equalizer forks (2) so boom hoist equalizer (3) cannot
fall off forks when step 6 is performed.
2. Disconnect lifting slings from mast butt.
3. Attach lifting slings from assist crane to lifting lugs (4,
View A) on mast top (5). Hoist so slings are just taut.
4. Remove bottom connecting pins (6, View B) and lift mast
top clear of mast butt.
5. Pay out wire rope from Drum 5 in mast butt while
performing step 6. Remember that MAX-ER Mast
Configuration in RCL must be selected.
6. Lift mast top away from mast butt and place mast top on
blocking in front of mast butt at dimension given in View
F.
7. Disconnect lifting slings from mast top.
8. Lay wire rope from Drum 5 on foundation alongside
mast butt and top so wire rope does not interfere with
installation of inserts.
Install 20 ft (6 m) Insert
See Figure 4-5 for the following procedure.
1. Attach lifting slings from assist crane to lifting lugs (4,
View G) on insert (9).
2. Lift insert into position at end of mast butt (View G) so
fixed pins (7, View C) in insert engage hooked
connectors (8) in mast butt.
3. Lower insert until bottom connecting holes line up and
install pins (6, View B).
Pins (6) are stored in pockets in the lacings next to the
connectors.
4. Lift insert so mast support pads are just off foundation
and securely block under end of insert (view G).
5. Disconnect slings from insert.
6. Store mast supports (see Figure 4-3
, View C):
a. Remove pads (8d) from working position and pin in
shipping position.
b. Tension cable with hand winch just enough to hold
mast supports legs (8b) in position when step 6d is
performed.
c. Remove pins (8c).
d. Retract mast support legs until pins (8c) can be
reinstalled.
CAUTION
Avoid Structural Damage to Mast Supports
Mast supports are designed to support only weight of 20 ft
(6 m) insert. Do not attempt to install 40 ft (12 m) insert on
end of 20 ft (6 m) insert while mast supports are deployed.
Legend for Figure 4-5
Item Description Item Description
1 Retaining Pin with Snap Pin (2 places) 6 Pin with Safety Pin (2 places)
2 Mast Top Fork 7 Fixed Pin (2 places)
3 Equalizer 8 Hooked Connector
4 Lifting Lug (4 places) 9 Insert — 20 ft (6 m)
5Mast Top