EasyManua.ls Logo

Manitowoc MAX-ER 16000 - Page 122

Manitowoc MAX-ER 16000
186 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Reference Only
SET-UP AND INSTALLATION 16000 HANGING MAX-ER® OPERATOR MANUAL
4-56
Published 04-17-17, Control # 067-11
Connect Beam to Counterweight — SEQUENCE 1
See Figure 4-29 for the following procedure.
1. Travel the crane in reverse and swing as required to
align connecting holes in beam assembly (2) with
connecting holes in counterweight tray (3).
2. Using remote control switch (on beam assembly), retract
and extend hanging counterweight lifting cylinder to
align connecting holes in beam assembly (2, View B)
with connecting holes in counterweight tray (3).
3. Install pins (4, View C).
4. Retract hanging counterweight lifting cylinder until straps
are just taut. Do not lift counterweight tray.

Table of Contents

Related product manuals