3 - 25
3 Operation
Grid Connect Photovoltaic Inverter KP100L-OD- USER’S MANUAL
3-6 Setting in Particular Countries
3
9
(7)
The Auto
Test of
OF
(7-1)The inverter turns on the inside Grid-connected
relay
(7-2)Detect level of OF is decreased at the point of
0.05Hz/s
(7-3)Grid-connected relays are disconnected, when OF
detect level keeps below the grid voltage for more
than OF detect time
(7-4)Detect level and detect time of OF detected in
(7-3) are shown. (Display for ten seconds.)
(8)
The Auto
Test of
UF
(8-1)The inverter turns on the inside Grid-connected
relay
(8-2)Detect level UF is increased at the point of
0.05Hz/s
(8-3)Grid-connected relays are disconnected, when UF
detect level keeps above the grid voltage for more
than UF detect time
(8-4)Detect level and detect time of UF detected in
(8-3) are shown. (Display for ten seconds.)
Items Sequences during the auto test LCD
The frequency of the grid
[e.g.] in the case of 50.00Hz
Setup level of OF
[e.g.] in the case of 50.30Hz
AutoTest:OF
50.00Hz / 50.30Hz
AutoTest:OF
50.01Hz / 90ms
Result of OF
Detect level of OF
[e.g.] in the case of 50.01Hz
Detect time of OF
[e.g.] in the case of 90ms
After displaying for ten seconds,
start the auto test of UF
The frequency of the grid
[e.g.] in the case of 50.00Hz
Setup level of UF
[e.g.] in the case of 49.70Hz
AutoTest:UF
50.00Hz / 49.70Hz
AutoTest:UF
49.99Hz / 90ms
Result of UF
Detect level of UF
[e.g.] in the case of 49.99Hz
Detect time of UF
[e.g.] in the case of 90ms
After displaying for ten seconds,
grid-connected operation is started
automatically and normal display is shown.