3 - 5
3 Operation
Grid Connect Photovoltaic Inverter KP100L-OD- USER’S MANUAL
3-2 Procedure at the First Time Operation
3
9
3-2
Procedure at the First Time Operation
Procedure at the First Time Operation
The procedure at the first time operation shows below.
(1) Connect the Solar modules to the KP100L.
(2) After the LCD becomes the display of the country setting, set a specified country.
(3) Make sure that the display of the country setting is correct.
(4) After turning OFF the AC breaker, wire the AC to the KP100L.
(5) Turn ON the AC breaker.
(6) Make sure that the KP100L starts running as indicated by the LCD.
Country Setting
Procedure of the Country Setting
The display moves to the display of the setting of the country when you start KP100L with Country Setting not
fixed. Refer to the figure below for setup. Table shows the relation between the menu and the country. You can't
set the country other than countries shown in the table. The KP100L complies with local and national standards
when correct country is selected.
Refer to P. 3 - 2 7 for the detect level in each country.
.
Menu [GER] [FRA] [GRE] [CZE] [DEN] [TUR] [RSA] [ESP] [POR] [ITA]
Country Germany France Greece Czech
Republic
Denmark Turkey Republic
of South
Africa
Spain Portugal Italy
After once setting the country setting, you can't change the country setting. Be careful when
you set it.
Significant property damage may possibly occur. Do not use the product with a mistake of
the country setting. Contact store purchased when you fix the country setting by mistake.