10 Operation
10-8
G5-series AC Servomotors and Servo Drives User’s Manual (with Built-in EtherCAT Communications)
10-3 Trial Operation
When you have finished installation, wiring, and switch settings, and have confirmed that status is
normal after turning ON the power supply, perform trial operation. The main purpose of trial operation is
to confirm that the servo system is electrically correct.
If an error occurs during trial operation, refer to Chapter 12 Troubleshooting and Maintenance to
eliminate the cause. Then check for safety, and retry trial operation.
Check the following items.
z Wiring
Make sure that there are no wiring errors (especially for the power supply input and motor output).
Make sure that there are no short-circuits. (Check the ground for short circuits as well.)
Make sure that there are no loose connections.
z Power Supply Voltage
Make sure that the voltage corresponds to the rated voltage.
Is the voltage stable?
z Motor Installation
Make sure that the Servomotor is securely installed.
z Disconnection from Mechanical System
If necessary, make sure that the load has been disconnected from the mechanical system.
z Brake Released
Make sure that the brake has been released.
z Connections to the Mechanical System
Are the load and Servomotor shaft properly aligned?
Is the load on the Servomotor shaft within specifications?
10-3-1 Preparations for Trial Operation
Inspections before Trial Operation

Table of Contents