410 Rockwell Automation Publication 7000L-UM301F-EN-P - March 2020
Chapter 5 Component Definition and Maintenance
Time Estimations
Operational Maintenance 0.5 hours per filter
Annual Maintenance
Initial Information Gathering 0.5 hours
Physical Checks
Torque Checks 2.0 hours
Inspection 2.0 hours
Cleaning ** 2.5 hours **
Meggering 1.5 hours
Control Power Checks
Contactor Adjustments ** 2.0 hours **
Voltage Level Checks 1.0 hours
Firing Check 0.5 hours
System Test ** 2.0 hours **
Medium Voltage Checks
Final Inspection 0.5 hours
Phasing Check ** 1.5 hours **
Autotuning** 2.0 hours **
Operation to Maximum Load Site Dependent
Additional Tasks
Investigation ** Depends on Nature
of the Problem **
Informal Training/Refresher ** 2.0 hours **
Spare Parts Analysis ** 1.0 hours **
Vacuum Bottle Integrity Check ** 3.0 hours **
Final Report 3.0 hours
** indicates that the time may not be required depending on the nature of the
maintenance and the condition of the drive system. These times are only
estimations.
Tool / Parts / Information Requirements
The following is a list of the tools recommended for proper maintenance of the
PowerFlex 7000 drives. Not all of the tools may be required for a specific drive
preventive procedure, but if we were to complete all of the tasks listed above the
following tools would be required.
Tools
100 MHz Oscilloscope with minimum 2 Channels and memory
5kV DC Megger
Digital Multimeter
To rq u e Wre n c h