Getting Started
  Installing the Display and Control Unit
  The following options are available for installing the control unit: 
(the pictures depict the SIW*DCP model)
§ Fastening the display and control unit to the weighing platform:
§ Guide the display and control unit onto the retainer bracket.
§ Level the weighing platform (see page 7).
–  Attached to the weighing platform
–  On the YDH01P column: optional for the DCP model
–  On the YDH02P column: optional for the BBP model
–  On the YDH0xCWS column: optional for the DCS model
–  On the YDH02CWP column: optional for the EDG model
  Operating the display and control unit separately:
§ Turn the weighing platform over and place it on a soft surface to avoid damaging the 
weighing system.
§ Remove the display and control unit retainer bracket.
§ Take the cable out of the cable channel.
§ Turn the weighing platform right side up and place it so that it rests on its feet.
§ Level the weighing platform (see page 7).
  Installing the display and control unit on the YDH01P column: 
§ Turn the weighing platform over and place it on a soft surface to avoid damaging the 
weighing system.
§ Remove the display and control unit retainer bracket.
§ Take the cable out of the cable channel.
§ Use the four hexagonal screws provided (M4+8) to attach the column to the weighing 
platform (back panel facing downward).
§ Turn the weighing platform right side up and place it so that it rests on its feet.
§ Loosen the two locking bolts at the top of the column to facilitate installation of the 
display and control unit.
§ Use the three hexagonal screws (M4x8) to attach the display and control unit to the top 
of the column.
§ Adjust the display and control unit to the desired angle and secure it there.  
– This is done by tightening the locking bolts on the top of the column.
6