Option 4: Cup & Cool
► Open the door.
► Pull the milk hose adapter out of the lid.
► Connect the desired milk nozzle (1 mm – 1.7 mm), if not already present, between the
hose and the adapter.
► Remove and rinse the milk container.
► Fill in fresh, pre-cooled milk (3 – 5°C).
► Place the milk container back in the cooling unit.
► Push the hose adapter back into the lid.
► Close the door.
Option: Under-machine cooling unit
► Open the door.
► Remove and rinse the milk container.
► Fill in fresh, pre-cooled milk (3 – 5°C).
► Place the milk container into the cooling unit.
► Hang the hose into the container.
The hose end must be in contact with the container floor.
► Close the door.
Machine powder
Danger of injury on the rotating dosing augers!
Never reach into the powder container while the device is switched on.
CAUTION!
Risk of machine
damage!
Danger of blockage through filling with unallowed powder!
Never fill anything other than powder for automatic operation into the powder contain-
er.
Ensure that the filled milk does not touch the closed milk container lid.
The milk nozzles included in the scope of supply (1 mm - 1.7 mm) have an influence on the
milk temperature. Milk foam that is too cold requires a smaller nozzle diameter. Milk foam that
is too hot requires a larger nozzle diameter.