20
8027872/1JTM/0-8/2023-05| SICKO P E R A T I N G I N S T R U C T I O N S | FLOWSIC550
Subject to change without notice
6 MOUNTING
6 Mounting
6.1 Safety
6.2 Scope of Delivery
The measuring device is delivered preassembled in sturdy packaging.
▸ Inspect for transport damage when unpacking the device.
▸ Document any damage found and report this to the manufacturer.
Scope of delivery
▸ Check the scope of delivery for completeness.
The standard scope of delivery comprises:
● Measuring device (meter body and SPU, already fitted)
● Mounting material
WARNING: Hazards during installation work
▸ Do not carry out any welding work on lines with meters fitted.
▸ Comply exactly with mandatory and approved methods.
▸ Observe and comply with regulations of the plant operator.
▸ Meticulously check completed work. Ensure leak tightness and strength.
Otherwise hazards are possible and safe operation is not ensured.
WARNING: Hazards through the gas in the system
The following conditions can increase the risk:
● Toxic gas or gas dangerous to health
● Explosive gas
● High gas pressure
▸ Only carry out installation, maintenance and repair work when the system is non-
pressurized.
WARNING:
▸ Observe applicable valid regulations, general standards and guidelines.
▸ Observe local safety regulations, operating instructions and special regulations.
▸ Observe the safety information in this document.
▸ Persons carrying out installation work must be familiar with the directives and stan-
dards applicable for pipeline construction and have the corresponding qualifications.
NOTICE: VCI corrosion protection
Remove the protective foam inside the meter body before mounting the device.
Otherwise, the device may be damaged and the measuring characteristics could be
impaired.
NOTICE:
Do not put the measuring device into operation if you notice any damage!