Installing the S7-400
2-22
S7-400 and M7-400 Programmable Controllers, Installation Manual
C79000-G7076-C424-01
2.9 Installing the Cable Duct
Procedure
1. Install the cable duct in the 19-inch pitch directly under the rack or between two
racks. Use M6 size screws for mounting.
The following figure shows how to mount the cable duct between two racks.
19-inch reference level
www.PLCworld.cn