PRE-OPERATION FUNCTION TEST
1323RD&1623RD Operation Manual 6-9 © Mar. 2022
EMERGENCY LOWERING
After pressing the emergency lowering combination
buttons, the platform can be lowered, even though
the engine is not started.
REGENERATION FUNCTION
1. Set the engine at low idle speed, and wait for the
coolant temperature to reach 60.
2. Push upward the regeneration interlock switch (-
toggle switch).
3. Press and hold the regeneration request switch
(self-reset switch) for 10s, and the regeneration
execution indicator light at the hour meter will be
lit.
4. Release the regeneration request switch for 3s,
and the regeneration request indicator light and
regeneration execution indicator light at the hour
meter will be lit and flashing separately.
5. Press and hold the regeneration request switch
for 3s, and the high exhaust temperature indicator
light and regeneration execution indicator light at
the hour meter will be lit, the engine speed will be
automatically increased, and the regeneration will
be performed.
Note:
Other actions cannot be performed while the
regeneration is executed. After completing
regeneration operation, push down the
regeneration interlock switch to turn off the
regeneration function, or wait for half an hour to
automatically exit this state.
Under normal circumstances, the next
regeneration operation cannot be executed until
50 hours after the previous regeneration
operation. But in the event of a regeneration
alarm, this restriction is not working.
TESTING THE PLATFORM
CONTROLLER (DTC
SYSTEM)
NOTICE
All tests on the platform controller should be
completed in one cycle.
!