4 Assembly and setting up
4.2 Assembling machine
4-10
Set the protective motor switch in accordance with the mains voltage:
DANGER
High voltage!
Electrical shock may cause death or serious injuries.
Î Deenergize building mains supply before opening the housing.
1. Open the mains switch housing.
Fig. 4-8 Protective motor switch Q1
2. Set the protective motor switch Q1 (1) in accordance with the mains
voltage of the building mains supply.
3. Close the main switch housing.
The knitting machine must be connected in the clockwise phase
sequence.
The mains supply is either led from the floor (1) to the main switch or from
the ceiling (2) through the right support of the yarn feeding and control
device to the main switch.
Fig. 4-9 Mains supply
Connect mains supply to
the main switch