39
6 Commissioning
Proper commissioning is essential for the system, to protect it against fires,
injury and electric shock.
6.1 Inspection before Commissioning
Check the following items before starting the inverter:
1. All the installation sites are convenient for operation, maintenance and
service.
2. Check and confirm that the inverter is firmly installed.
3. Space for ventilation is sufficient for one inverter or multiple inverters.
4. Nothing is left on the top of the inverter or battery pack.
5. The inverter and accessories are correctly connected.
6. Cables are routed in a safe place or protected against mechanical
damage.
7. The selection of the AC circuit breaker is in accordance to this manual
and all applicable local standards.
8. All unused terminals at the bottom of the inverter are properly sealed.
9. Warning signs and labels are suitably affixed and durable.
6.2 Button Function
Inverter offers two buttons with multiple functions. Please refer to the following
table before any operation of the inverter.
Tab. 6-1 Button function