Maintenance
6-- 12
TPS2000 Series Digital Storage Oscilloscopes Service Manual
Installation. To install the front case, refer to Figure 6--4 and follow these steps:
1. Place the front case face down on a soft surface.
2. Ensure that the switch keypad is aligned and feeds through the front case.
Follow the procedure on page 6--19.
3. Align the power switch, BNC connectors, and knob shafts so they feed
through the front case.
4. Lower the chassis onto the front case.
5. Install the four screws on the inside of the chassis that attach the chassis to
the front cover. See Figure 6--4.
6. Follow the procedures on page 6--7 to install the rear case.
7. Install the plastic BNC shells onto the BNC connectors.
8. Use the 16 mm (5/16 inch) deep socket and install the BNC nuts onto the
BNC connectors. Torque the nuts to 40 in-lbs using the torque wrench.
9. Install the BNC cover and front-panel knobs.