Vertiv | Liebert® CRV4 | User Manual 50
Start-up Commissioning
5.3. Inspection After Commissioning
Once the commissioning is completed, the Vertiv engineers will conrm the same using the checklist in
Table 5-1.
Table 5-1 After Commissioning Inspection Checklist
Particulars Conrmation
Check all outputs are functional.
Check that the temperature & humidity settings as well as the control precisions are congured
correctly within range.
Check and conrm that all the output functions are automatic.
Is there any abnormal alarm.
Ensure that electrical installation checklist is conrm, refer Table 4-4.