Position of the Operator 6.12
43
[en-US] | 09/2022 | 5100061327 | RTLx-SC3 | Operator’s Manual
Note: Non-compactible material or flaws in the substrate are detectable by
the system if they are more than one meter in length. With sudden changes
from high to low compacted soil (or vice versa), there is a slow rise or fall in
the LEDs.
Testing
Test the Compatec compaction system upon machine start up.
1. Rotate the starting key clockwise to the ON (I) position.
2. Observe the LED display. During the first few seconds after turning the
starting key to the ON (I) position, the eight LEDs illuminate from left to
right.
If Then
All LEDs illuminate, The system is fault free and the LEDs switch off in succession. Then, all eight LEDs
flash briefly with reduced brightness.
All LEDs illuminate and re-
main illuminated after initial-
ization,
The sensor is not functioning properly.
6.12 Position of the Operator
Although the receiving eyes on the machine can receive signals from any di-
rection, the switches on the transmitter are positioned so that they corre-
spond to the movements of the machine with the operator standing BEHIND
it.
wc_gr012177
2m (6.6 ft.) 2m (6.6 ft.)
OK
OK
OK
2m (6.6 ft.)
2m (6.6 ft.)
Fig.14: Position of the operator