48
EPG S2
OPERATING MANUAL
VERSION 09/2017 ORDER NUMBER DOC2317574
Section Type of inspection Requirements Inspection
by
Type of inspection Inspection
interval
7 Measures to take if the work pieces
are insu ciently grounded
If su cient work piece grounding
in accordance with section 6
cannot be ensured, appropriate
equipment, e.g., ionizers, must
be used to discharge electric
charges on the work piece. Such
equipment must not exceed the
permitted discharge energy of the
spray systems with which it is used.
In terms of permitted discharge
energy, this equipment must be
put through the same inspections
as the powder spray systems used
with it. The discharge equipment
must be interlocked with the spray
system such that the high voltage
is switched o and that coating
cannot take place if the discharge
equipment malfunctions.
SP ME/FU/SÜ
Measurement of discharge
energy, check the monitoring
equipment's test function by
triggering it.
weekly
8E ectiveness of the manually
or automatically actuated re
extinguishing systems
(room protection system)
E ectiveness of the manually
or automatically actuated re
extinguishing systems
(room protection system).
HE/BSB FI
Trigger re extinguishing
system, observe manufacturer's
requirements.
6 months
Legend:
MF = Manufacturer
ER = Employer
SP = Skilled person
FPO = Fire prevention o cer
ELT = Electrician
TP = Trained person
FI = Function inspection
ME = Measurement
OC = Organization check
VI = Visual inspection
CM = Constant monitoring