First Time Power-Up and Start-Up
5
5-2 | CFW-11
5. Return the inverter covers.
6. Measure the power supply voltage and verify if it is within the range listed in Chapter 8 TECHNICAL
SPECIFICATIONS on page 8-1.
7. Apply power to the input:
Close the input disconnect switch.
8. Check the result of the first time power-up:
The keypad should display the standard monitoring mode (Figure 4.3 on page 4-3) and the status LED
should be steady green.
5.2 START-UP
The start-up procedure for the V/f is described in three simple steps by using the Oriented Start-up routine
and the Basic Application group.
Steps:
1. Set the password for parameter modification.
2. Execute the Oriented Start-up routine.
3. Set the parameters of the Basic Application group.