6.5.4 Wet cleaning of turbine and nozzle ring
Prerequisites:
Procedure without automated cleaning
The following operating state and the following prerequisites have been tested and ap-
proved by ABB Turbo Systems for cleaning operations:
u Set the engine load between 20…50% so that the turbine inlet temperature is between
380…430°C.
Fig.24: Turbine and nozzle ring cleaning cycle
u Once the turbine inlet temperature is stable and has dropped below 430°C, wait at least
another 10 minutes to allow the turbine-end turbocharger parts to cool down.
u Start the cleaning cycle according to the following description Wet cleaning procedure.