ABB Network Partner AB
Interlocking
Version 1.0-00
1MRK 580 151-XEN
Page 6 - 188
6.2 Signal list
6.2.1 ABC_LINE
Table 1: Input signals for ABC_LINE
IN: DESCRIPTION:
IFxx-Q0_OP Signal is 1 if Q0 is open
IFxx-Q0_CL Signal is 1 if Q0 is closed
IFxx-Q9_OP Signal is 1 if Q9 is open
IFxx-Q9_CL Signal is 1 if Q9 is closed
IFxx-Q1_OP Signal is 1 if Q1 is open
IFxx-Q1_CL Signal is 1 if Q1 is closed
IFxx-Q2_OP Signal is 1 if Q2 is open
IFxx-Q2_CL Signal is 1 if Q2 is closed
IFxx-Q7_OP Signal is 1 if Q7 is open
IFxx-Q7_CL Signal is 1 if Q7 is closed
IFxx-Q51_OP Signal is 1 if Q51 is open
IFxx-Q51_CL Signal is 1 if Q51 is closed
IFxx-Q52_OP Signal is 1 if Q52 is open
IFxx-Q52_CL Signal is 1 if Q52 is closed
IFxx-Q8_OP Signal is 1 if Q8 is open
IFxx-Q8_CL Signal is 1 if Q8 is closed
IFxx-Q15_OP Signal is 1 if Q15 on busbar A is open
IFxx-Q15_CL Signal is 1 if Q15 on busbar A is closed
IFxx-Q25_OP Signal is 1 if Q25 on busbar B is open
IFxx-Q25_CL Signal is 1 if Q25 on busbar B is closed
IFxx-Q75_OP Signal is 1 if Q75 on busbar C is open
IFxx-Q75_CL Signal is 1 if Q75 on busbar C is closed
IFxx-C_DC_OP All line disconnectors on bypass busbar C
except in the own bay are open
IFxx-BC_AB_CL There exists a bus coupler connection
between busbar A and B
IFxx-BC_AC_OP There is no bus coupler connection
between busbar A and C
IFxx-BC_AC_CL There exists a bus coupler connection
between busbar A and C
IFxx-BC_BC_OP There is no bus coupler connection
between busbar B and C
IFxx-BC_BC_CL There exists a bus coupler connection
between busbar B and C
IFxx-VOLT_OP There is no voltage on the line and not fuse
failure
IFxx-VOLT_CL There is voltage on the line or there is a VT
(fuse) failure