EasyManuals Logo

Applied Precision PTE 2300 Series User Manual

Applied Precision PTE 2300  Series
114 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #44 background imageLoading...
Page #44 background image
Portable Test Equipment
User’s Guide
PTE-UGFW56a-EN www.appliedp.com
44
5.2.3 Maximum Demand Test
This page can be accessed from Load Values screen by double press of F3.
Configuration of MD tests is in Test Settings menu, where Period, Subperiods and Window can be
specified. The duration of MD test is identical with Dial test duration and it is recommended to be at
least two times greater than period of MD test.
Test is started with F1 key. Then the Energy (E) is being summed and the average power (MD Act.) is
being calculated. Operator must be aware of the number already stored in electricity meter’s
Maximum Demand Register. It is highly advised to delete such meter’s register before and after MD
test. This operation will ease the whole test procedure.
During MD test the icon above F1 depicts the sign of play. In this state the test can be prematurely
stopped by F1 and the icon changes to stop sign. To evaluate the MD test, it is compulsory to wait
until the test stops automatically or at least wait until the time End passes because only then the
MD Reg.will obtain value different from zero. This is the value which is compared with the meter’s
MD register. When the test is ceased, Enter MD registermessage flashes until any key is pressed.
This warning informs the operator to submit the value of MD register from meter. Then the overall MD
error is calculated.
Dial Test runs always simultaneously with Maximum Demand Test which has to last longer than Dial
Test. The reason lies in principle of Dial Test evaluation. This feature offers also evaluation of these
two tests concurrently.
Meter connected to the network can measure quantities via transformer. In such case meter’s
parameters can be defined for transformer’s secondary side or calculated to the primary side (upper
switch Sec / Prim). By default, both Prim. / Sec. switches and CT/VT ratios are acquired from
database. They can be changed (they turn red). These switches along with CT / VT ratios enable to
set where the meter is placed (during measurement) and where the device measures energy.
Maximum Demand Test screen
* P94
Content:
Sec. / Prim. ....... Meter measures energy for primary or
secondary side of transformer (if
applicable). Default state is Sec.
MD ..................... Register value from meter after the test
CT .................... Current Ratio
VT ..................... Voltage Ratio
Prim. / Sec. ...... Side of transformer on which is the
energy measurement carried out
3P3W ................ Actual Connection Type
Error ............. Error calculated from MD and MD Reg.
MD Act. ......... Actual average power
MD Reg. ........ Power value obtained after defined time
(End)
E ................... Energy measured during the test
....................... Last tri quantities show two values with
respect to Prim. / Sec. switches
Begin ............ MD test timestamp of beginning of window
End ............... Duration of the test in minutes
<Progress bar> .... Graphical interpretation of duration of the
test

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Applied Precision PTE 2300 Series and is the answer not in the manual?

Applied Precision PTE 2300 Series Specifications

General IconGeneral
BrandApplied Precision
ModelPTE 2300 Series
CategoryPortable Generator
LanguageEnglish