Commissioning
EL70x1162 Version: 4.4
Fig.186: Process Data tab SM3, EL70xx (default)
5.7.2 PDO Assignment
In order to configure the process data, select the desired Sync Manager (SM 2 & 3 can be edited here) in the
upper left-hand "Sync Manager" field (see fig. Process data tab SM2, EL70xx (default) and SM3, EL70xx
(default)). The process data assigned to this Sync Manager can then be switched on or off in the “PDO
Assignment” box underneath. Restarting the EtherCAT system, or reloading the configuration in
configuration mode (F4), causes the EtherCAT communication to restart, and the process data is transferred
from the terminal.