Installation, Operation and Maintenance Manual
VCIOM-08500-EN
Storage and Pre-Installation
Section 2: Storage and Pre-Installation
Figure 6
2.3 Checks to be Performed Before Installation
Make sure that the valve to be motorized is appropriate for coupling to
the actuator.
The electrical supply cables must be suitable for the power rating
(refer to the test certicate that comes with the actuator).
Gather the right tools for assembly and for setting the actuator controls.
If the actuator has been stored for a long period of time prior to its installation, make sure to:
Check the condition of the O-ring seals.
Check the installation of the plugs or conduit glands on the conduit entries.
Check if the enclosure covers or the actuator body are cracked or broken.
Check the oil level in the actuator and top up if necessary.
Put the batteries back into place
(see Section 11.3, Maintenance - Lithium battery change).