Start-up procedure9
Logamax plus GB162-80 kW/100 kW - Subject to modifications resulting from technical improvements!56
9.11 Carry out a function test
z During initial start-up and annual inspection and/or
needs-oriented servicing, make sure that all control,
regulating and safety devices are in full working order
and, if applicable, check them for correct adjustment.
z The gas and water circuits must be tested for leaks (see
paragraph 9.1, page 46 and paragraph 9.9, page 54).
9.12 Measure the ionization current
z Press on the control panel to open it.
z Open at least two thermostatic radiator valves, if present.
Do not switch ON the boiler.
z Switch OFF the heating system by pressing the main
switch of the BC10 basic controller (fig. 66, pos. 1).
z Turn the vent key through a quarter turn to undo the
boiler door lock (fig. 47).
z Push the fastener down (fig. 47) and open the boiler
door.
z Undo the plug and socket connection of the monitoring
cable (fig. 67).
Fig. 66 BC10 basic controller
888
1
123 456
11
10 98
7
110
140
130
120
90
100
130
170
150
90
110
190
Fig. 67 Removing the ionization electrode plug and socket
connection