Installation 6
Logamax plus GB162-80 kW/100 kW - Subject to modifications resulting from technical improvements! 15
6 Installation
6.1 Requirements for the installation room
6.2 Installing the boiler
Observe the installation distances of the combustion air/flue
gas system.
z Before starting installation check that the carrying
capacity of the wall is sufficient for the boiler weight.
z Remove the packaging and dispose of it in an environ-
mentally manner.
z Measure the installation height (see chapter 4 "Dimen-
sions and connections", page 11).
DANGER
z Install the heating system in a frost-free
room.
z If the boiler is operated dependent on room
air, the installation room must have the
required air vents. DO NOT obstruct these
vents. The air vents must always be free.
z When installed in a room with thin walls or a
thin floor, resonating noise may occur. Install
noise reducing parts if required.
z Do not store any flammable materials or
liquids in the immediate vicinity of the boiler.
z Never use any chlorinated detergents or
halogenated hydrocarbons (e. g. in spray
cans, solvents and detergents, paints,
adhesives).
z Do not allow too much dust to collect on the
boiler.
NOTICE
z To protect the connection orifice you must
not remove the styrofoam bottom panel.
z Do not lift the boiler by the door covering the
control panel, see paragraph 5.2, page 13.
z Protect the boiler and the combustion
air/flue gas orifice against pollution during
installation.